25m of weak sediments in the upper soil layer
The key challenge was to provide the technical proof of a monopile foundation for an 8 MW wind power plant in very difficult subsoil conditions of the Arkona Basin of the Baltic Sea and at a water depth of up to 45 m. In cooperation with Gud Consult GmbH, JBO Ingenieure GmbH, HPC – Hanseatic Power Cert GmbH and Siemens Gamesa Renewable Energy, S.A., it was possible to provide technical proof of feasibility for the statics, design, production and offshore installation.